2.product parameter
size | 125002500x3500mm |
payload | 50ton |
tare weight | 7500kg |
axle | 3x13ton/14ton/16ton/20ton brand can be opentional |
suspension | mechanical suspension/air suspension/american type/germany type can be opentional |
tire | 11R22.5/12R22.5/11.00R20/12.00R20 brand can be opentional |
wheel rim | 8.25/9.0/8.0/8.5 |
kingpin | 2"/3.5" |
I beam | up:14mm;bottom:16mm;middle:8mm;height:500mm;width:140mm:material:Q345B |
landing gear | jost c200 /fuwa two speed 28ton |
floor/side board | 3mm checkered plate/600mm;800mm;1000mm board opentional |
twist lock | 12pcs use for 1x40ft or 2x20ft (opentional) |
spare tire carrier | 2 pcs |
tool box | 1 or more can be opentional |
air wiring | doule air line ; |
electricity wiring | 6 core wiring;24v or 12v ;LED lamp; |
brake system | wabco relay valve;drum brake;t30/30 brake chamber |
paiting |
complete chassis sand blasting;electrophoresis coating;1 coat of anticorrosive prime; 2 coats of final paiting |
colour | opentional |
accessories | brake shoe;spare tire cranking;shaft head wrench;jack 50ton;tire bolt;lamp |
BRIEF DEscriptION
the normal produce process is very important.it can be influence the quality-durable years of the product .even the customer confidence to our product.
3.NORMAL PROCEDURE
1)cutting
use the plasma cutting machine cut the steel to little parts use for suitable welding and splicing
2)welding
after steel cutting process the next step is welding .this process the main work is beam welding .the top plate-bottom plate and the
middle plate will be welding together . this process will be use submerged arc welding process.this type of welding is very
special .its exclusively used in I beam welding .after this welding process other parts of the trailer will be use different welding way
for different steel-argon arc welding-electric arc welding-manual welding-gas welding and so on
3)blasting
this process is use for the first step of surface cleanness-stress relief-derusting before paiting .